This is the compatibility page for the inpower

1. Compatibility

a. Compatible Connected Device(s)

  • Model(s): INPower INPPCS-100/0.4-W-14-C1-OS
  • Firmware version: ARM:6796; FPGA:782

b. Battery

  • Model(s): Solar MD SS7xxx series; SS8xxx series
  • Firmware version: 183 or higher

c. Datalogger

  • Model(s): Solar MD LoggerV2 Hw:2.20 / 2.21
  • Firmware version: 9.107 or higher

2. Disclaimer

This guide is intended to be used as a supplement to all manuals and documentation provided by device manufacturers. In case of discrepancies or conflicts, contact Solar MD Technical Support immediately.

3. Installation

  • Only qualified personnel should work on electrical equipment.
  • Wear necessary PPE when working with electricity.
  • Read and follow all device manuals.
  • Refer to the SolarMD Quick User Guide for communication cable termination.
  • Electrical wiring must comply with local standards.
  • Ensure mechanical and electrical integrity:
    1. Earth resistance test and bonding continuity
    2. Polarity test
    3. Torque and mark all bolts and terminations
    4. AC cable insulation testing
    5. DC bus insulation testing (see SMD_IRT-DCB_01)

4. Cold Commissioning

  • Visually inspect for safety: covers in place, no live parts accessible.
  • Turn on all batteries using the green ON/OFF switch on the BMU.
  • On MyPower24 portal:
    1. Go to Logger > Interfaces tab → press Scan → connect found battery.
    2. In Battery > Settings:
      • Set Cluster Remote Device to InPower
      • Set CANBUS Baudrate to 250kbps
    3. In Battery > Cluster Data:
      • Identify the Master battery
      • Confirm “Online Batteries” = number of installed batteries
    4. In Battery > Actual Data:
      • Confirm all battery voltages are within 10V of each other

5. Hot Commissioning

  • Turn on battery isolators → wait ~5s for precharge and main relay
  • Confirm in Battery > Cluster Data: “DC BUS Connected Batteries” = installed batteries
  • Power on:
    1. External DC switch (if present)
    2. Grid breaker on PCS (PCS should start in ~1 min)
  • On MyPower24 portal:
    1. In Logger > Interfaces tab:
      • Select eth0
      • Click Add Device → select InPower
      • Enter serial number, IP, etc. → click Start
      • Blue balloon should appear in My Devices
    2. In PCS page:
      • Set battery type to Lithium-ion

!! IMPORTANT: Incorrect battery type may cause damage and void warranty.

  • Configure grid settings per local code
  1. In Battery > Cluster Data:
  • Check:
    1. Can State = Enabled
    2. Line State = Connected
    3. Bit Rate = 250kbps
    4. Tx/Rx frames increase every ~3 seconds
    5. Note: If baud rate is changed, restart PCS to reset CANBUS controller
  • Once communication is confirmed, switch PCS on for testing
  • Start PCS:
    1. Off-grid: no load
    2. Grid-tied: low charge/discharge power
  • Verify AC/DC voltage and current match portal data
  • Check for proper function of batteries, PCS, and other devices
  • Disconnect CANBUS temporarily:
    1. PCS should show BMS Communication Fault in ~10s
    2. Reconnect → PCS should recover in ~3s
  • Perform high current test:
    1. In Battery > Remote Device Control Test:
      • Set charge/discharge current to 0A for 20s
      • Battery current should drop to 0A and recover automatically
    2. Ensure:
      • Battery room is climate-controlled (20°C–30°C)
      • PCS has adequate cooling
      • Use thermal camera to verify no overloaded cables or loose connections
You could leave a comment if you were logged in.
Previous Next

Site Tools

  • Recent Changes
  • Media Manager
  • Sitemap

Page Tools

  • Show pagesource
  • Old revisions
  • Backlinks
  • Back to top

User Tools

  • Log In
products/high_voltage/compatibility/inpower.txt · Last modified: 2025/05/15 13:57 by masud
wiki

Table of Contents

Table of Contents

  • 1. Compatibility
    • a. Compatible Connected Device(s)
    • b. Battery
    • c. Datalogger
  • 2. Disclaimer
  • 3. Installation
  • 4. Cold Commissioning
  • 5. Hot Commissioning
  • Discussion
  • bms-ex
  • old
  • products
  • services